JSA FOR SHUTTERING WORK
Name of the Site               --       Name of the project or site
Date of the JSA                --       18/01/2022
Name of the Preparation -- YOUR NAME
| S.No | Scope of Activity | Hazard | Control Measures | Requested by | 
| 1) | Planning & arranging materials | ·        
  Inadequate
  access, ·        
  poor
  selection of equipment, ·        
  inadequate
  employee  
 | ·        
  Work site
  assessment completed, and Scope of works completed including listing of
  equipment requirements, staffing levels, site hazards and difficulties.   ·        
  Arrangements
  will be made for delivery schedule of materials. 
 | 
 | 
| 2) | Delivery
  of materials and site set up 
 | ·        
  Delivery
  of materials and site set up ·        
  Site
  unknown to workers – lead to possible ·        
  incidents
  involving other contractors, and site hazards | ·        
  Small
  materials will be palletized and delivered by truck with mounted crane by
  (less than 10 tonne) for unloading.  ·        
  Larger
  materials will be delivered by truck with slewing crane with certified
  operator and dogman for unloading. ·        
  Team to
  be provided with site induction on arrival by Principal Contractor.  ·        
  Site
  notices to be posted and barriers put in place as needed.  ·        
  PPE must
  be worn at all times (include hard hats, safety shoes, flour wear | 
 | 
| 3) | Inspection of Timbers & Equipment | ·        
  Risk of
  splinters and cuts to workers. ·        
  Possible
  risk of failure of timbers and  equipment | ·        
  All
  timbers will be visually inspected at commencement of the job.   ·        
  Barbs,
  nails etc will be removed with pliers, tools. ·        
  Structurally
  Defective timbers are removed from use.  ·        
  All
  timber and equipment will be inspected and  serviced as required by manufacturer recorded
  on the plant and equipment register.  ·        
  Faulty
  plant and equipment will be tagged out of service and removed from site. | 
 | 
| 4) | Erection
  of formwork  | ·        
  Risk of
  being hit by plant such as  excavators ·        
  hit by
  debris  ·        
  work like
  brick layers, demolition works, jip rockers and services trades etc. | ·        
  Use
  barrier via tap or other wise to seal off areas where work is being carried
  out away from any plant machinery operating.  ·        
  PPE must
  be worn at all times (include hard hats, safety shoes, flour wear. | 
 | 
| 5) | Erection of Formwork support & Structure | ·        
  instability
   formwork ·        
  Tripping
  Hazard ·        
  Falling
  Hazard ·        
  Ergonomic
  Hazard  
 | ·        
  All
  formwork supports, structures and attachments are inspected for defects prior
  to operations.  ·        
  Defective
  equipment will not be used. ·        
  Hardhats
  and Steel capped boots ·        
  Engineer
  to complete hand-over certificate for  structure
   ·        
  Use
  structure as per manufacturers recommendations.  ·        
  Risk of
  tripping and falling when attaching timbers to framing if no work platform available.   ·        
  Working
  on windy or wet days ·        
  Working
  From heights more than 1 frame high can lead to falling in excess of 2 meters.
   ·        
  Temporary
  work platforms to be put in place when attaching framing. Platforms to meet
  scaffolding standards.  ·        
  Handrails
  need to be erected on leading edge and post to be screwed down with screws.  ·        
  Harnesses
  need to be worn and secured to a strong support if a person is to work beyond
  handrails  ·        
  If
  platform is in working progress and hand rails are not erected yet, ·        
  Personnel
  must stay away at least 2 meters from leading edge.  ·        
  PPE must
  be worn at all times (include hard hats, safety shoes, flour wear  ·        
  Workers
  are not to work in windy or slippery condition on the formwork deck. ·        
  A
  platform made up of planks which is to be at least 450mm in total width is to
  be erected on top of the first set of frames to prevent a fall greater than 2
  meters to a hard surface.  ·        
  The same
  will apply when striping high formwork. | 
 | 
| 6) | Plying 
 | ·        
  Fall from
  height ·        
  Tripping
  Hazard ·        
  when wet
  or windy conditions are present.  ·        
  Stepping
  on nail in plywood | ·        
  Erection
  of fall protection when working at  height
  – Scaffolding will be used if in situ. ·        
  Alternatively
  hand-rail guarding will be erected.   ·        
  Denial
  and always work in safe weather conditions | 
 | 
| 7) | Woking next to train line | ·        
  Woking
  too close to train line can lead to shock from train power lines or even collision
  and death with an on passing train | ·        
  Don’t go
  any were near train lines and always keep a safe distance from them. For the purpose
  out works, there is no work to be carried out any were near the train lines. | 
 | 
| 8) | Power
  Tools 
 | Possible
  Hazards   - Cut to
  limbs -
  Electrocution - Many
  circular saws working in close  proximity
  may cause hearing damage. May damage sight due to flying debris | Possible
  Hazards   - Cut to
  limbs -
  Electrocution - Many
  circular saws working in close  proximity
  may cause hearing damage. May damage sight due to flying debris | 
 | 
| 9) | Stripping 
 | ·        
  Risk of
  being struck by falling building –  ·        
  ceiling,
  floor if support frames are dropped. ·        
  From
  under the structure–‘drop stripping’.  ·        
  Risk of
  puncture injury if nails are left in timbers when being stripped, all nails
  should be De-nailed as being stripped. ·        
  Risk of
  being hit by falling object if access to area where stripping is undertaken
  is not secured. | ·        
  Drop
  stripping is prohibited for all works. ·        
  All
  support jacks will be lowered incrementally with appropriate supports left in
  situ to minimise risk being hit by falling object. ·        
  Ply will
  be removed sheet-by-sheet from the concrete.  ·        
  All timbers
  will be de-nailed as stripping occurs stored immediately.  ·        
  No nails
  will be left on work floor. ·        
  The work
  area will be cordoned off by appropriate tape and barriers and signage
  erected indicating unauthorised access denied ·        
  Only 2
  workers will be allowed to enter and work in the stripping area at one time.  ·        
  Workers
  will be appropriately trained. ·        
  Supervision
  will be provided. 
 | 
 | 
| 10) | Removal
  of Centralising Equipment 
 | ·        
  Form work
  materials left in area could lead to risk of trip/fall risk and inadequate access. ·        
  Risk of
  being hit by falling object when removing centralising equipment. | ·        
  All
  formwork equipment must be stacked and/or ·        
  palletised
  and removed from site immediately ·        
  after
  stripping and prior to removal of ·        
  centralising
  equipment too ensure adequate ·        
  access.  ·        
  Area to
  be cordoned off with tape and barriers ·        
  to
  prevent access to non-authorised personnel. ·        
  Signage
  to be erected  ·        
  Only 2
  competent staff members to remove ·        
  centralising
  equipment.  ·        
  Line of
  site supervision ·        
  Back
  propping to be erected prior to dismantling  ·        
  centralising
  equipment t allow adequate curing ·        
  time for
  cement. | 
 | 
| 11) | Shifting of Material  | ·        
  Personal injury. ·        
  Tripping Hazards ·        
  Slipping Hazard | ·        
  Leveling surface in required.  ·        
  Trained workman is required with
  right body posture. ·        
   Work space should be maintained properly
  without any obstruction. | Site engineer/EHS | 
| 12) | Placing of material | ·        
  Tripping hazards. ·        
  Personal injury ·        
  Slipping Hazard | ·        
  Access should be clear. ·        
  Material should be well stacked. ·        
  Adequate PPEs should be use. | 
 | 
| 13) | Handling of C.T props | ·        
  Hand tools. ·        
   Tripping Hazard ·        
  fall of persons | ·        
  Hand and power tools should be inspected
  and secured. ·        
  Shuttering boards should be
  secured. ·        
  All Access and egress should be
  clear. ·        
   Walkway should be free from loose material | 
 | 
| 14) | De shuttering | ·        
  Falling Hazard ·        
  Slipping Hazard. ·        
  Strike. | ·        
  The surrounding area should be
  barricade and caution boards place before work. ·        
  All workers should be trained
  regarding the de shuttering work. ·        
  Loose materials should not place in
  a access. ·        
  De shuttering should be taken place
  in systematic manner by removal of the shuttering in stage wise. ·        
  Unbalance area should identify and
  corrective action should be ensured. ·        
  There should not be any unsafe act
  at the time of de shuttering. ·        
   Staking and arranging all shuttering
  material at all time. | 
 | 
| 15) | Emergency Procedure | ·        
  Injury / damage as a result of
  Painting work 
 | ·        
  Training to be giving to all
  personnel to ensure understanding of all emergency arrangement at site. ·        
  Line supervision shall take control
  of any emergency situation until the emergency response team arrives. ·        
   Any area of danger shall be immediately
  condoned off. ·        
  All personnel shall immediately leave
  their work location and proceeding an orderly manner to the nearest emergency
  assembly point. ·        
   All personnel should be aware of the
  emergency contact details / numbers. ·        
  All personnel should be aware of the
  First Aides Room location. | 
 | 
